Kia Dealership in Scunthorpe. Civil Engineering.

All Foundations was asked to design and build a new Kia dealership on the grounds of an existing dealership. The scope of the contract meant that All Foundations had to use carefully selected sub-contractors to undertake certain aspects of the works.

Client: F. Cross & Sons (VW dealership)
Main Contractor: Allied Steel Frame Buildings
Value of Contract: £295,000.00
Scope of Works: Civil Engineering. Piled foundations / Steel framed building / Car parking and display area


case-study-0019

case-study-0020

case-study-0021



Click image to enlarge.
Having secured a new dealership, the client wished to expand its current V.W. dealership to encompass a new showroom within the grounds of its existing site.

Sub-contractors

Acting as principle contractor and working with specialist subcontractors, the new high tech building was constructed ahead of schedule and to the complete satisfaction of the client.

Scope of the works

All Foundation’s works initially involved the stabilisation of the existing poor ground using a vibro piled solution.

The building works included the construction of a showroom and workshop, along with the construction of a 3500m2 car parking and display area.

All of the works were carried out in and around a very busy existing dealership with little if any effect on their core trading activities.

Said Jim Usher, All Foundations engineer, “It was pleasing once again to be allowed to display the full range or our activities and also provide a high calibre customer with a simple, no hassle “one stop shop” package / solution.”